Project name: PSBP PF2 North East
Budget: £150m
Number of Pupils: 8,637

The batch consisted of 12 schools, 6 secondaries and 6 primaries. We were required to design 10 concurrently however the biggest challenge was that the 6 secondaries and 1 primary were all to be handed over the same summer. Through a great, integrated team effort we were able to achieve this and ensure all schools were ready to open in Sep 16.

 

Project name: Hessle High School and Sixth Form College
Budget: £18.6m
Number of Pupils: 1,550

The old school was spread across three differents sites requiring a large and complex decant. The build programme ultimately left only 4 days to decant the majority of the ICT equipment and install it in the new school building. The Ribui team achieved the target delivery date, on time and on budget.

 

Project name: Vaughan Primary
Budget: £6.6m
Number of Pupils: 630

The existing site included separate Juniors and Infants blocks with the former being replaced and the latter refurbished. The project involved a complex decant as the new block was handed over 6 months ahead of the refurb, with the infants students then moving to the old juniors in the interim to allow the refurb to begin. We therefore created a solution to integrate the old junior block ICT with the new ICT provision, handholding the school throughout this process and minimising any disruption.